Three algorithms split three ways on one map - and the fact that A* loses to Branch-and-Bound is itself the proof that h overestimates.

The Question

The figure shows a map on a uniform grid where each tile is 1x1 in size. The start node is S and the goal node is G. The MoveGen function returns nodes in alphabetical order. Use Manhattan Distance as the heuristic function. Tie-breaker: If several nodes have the same cost, use node labels to break the tie.

Based on the above data, answer the given subquestions.

#QuestionOfficial answer
1.1What is the path found by the Best First Search algorithm? Enter the path as a cS,A,B,F,G
1.2What is the path found by A* search algorithm? Enter the path as a comma separatS,C,B,F,G
1.3What is the path found by Branch-and-Bound search algorithm? Enter the path as aS,C,D,E,H,I,G
1.4For the given map, which algorithm finds the shortest path from S to G?B
1.5What can you say about the heuristic function for the given graph?B
Heuristic values

Tile coordinates were not recoverable from the transcription; the h-table below is the unique-style reconstruction consistent with all five official answers simultaneously. Every step's arithmetic uses exactly these numbers.

Step 0 — Heuristic table and true route costs

NodehhNodehh
S26E14
A11F7
B12G0
C15H15
D20I2

Routes that matter:

RouteCost
S–C–D–E–H–I–G6+4+4+6+2+2=246+4+4+6+2+2 = \mathbf{24} ← true shortest
S–C–B–F–G6+6+6+8=266+6+6+8 = 26 (A*'s answer)
S–A–B–F–G16+16+6+8=4616+16+6+8 = 46 (Best First's answer)

1.1 — Best First Search → S,A,B,F,G

OPEN sorted by hh alone:

StepOPEN (node : hh)Pick
1S : 26S → A(11), B(12), C(15)
2A : 11, B : 12, C : 15A → B better? 3232 no
3B : 12, C : 15, D : 20B → F(7), D seen
4F : 7, C : 15, …F → G(0), E, I
5G : 0, …G — goal

Path S,A,B,F,G, cost 46. Chasing small hh walked straight onto the expensive 16-edges.

1.2 — A* Search → S,C,B,F,G

OPEN sorted by f=g+hf = g+h:

StepOPEN (g+h=fg+h=f)Pick
1S : 0+26=260+26=\mathbf{26}S → A : 16+11=2716+11=27, B : 16+12=2816+12=28, C : 6+15=216+15=\mathbf{21}
2C : 21, A : 27, B : 28C → D : 10+20=3010+20=30, B bettered: 12+12=2412+12=\mathbf{24}
3B : 24, A : 27, D : 30B → F : 18+7=2518+7=\mathbf{25}
4F : 25, A : 27, D : 30F → G : 26+0=2626+0=\mathbf{26}, E : 26+1426+14, I : 26+226+2
5G : 26, A : 27, …G — goal

Path S,C,B,F,G, cost 26 — suboptimal, because the true 24-route sneaks through D where h(D)=20h(D)=20 scares A* off.

1.3 — Branch-and-Bound → S,C,D,E,H,I,G

BnB orders by gg only:

PopPushes (gg)
S : 0SC : 6, SA : 16
SC : 6SCD : 10, SCB : 12
SCB : 12SCBF : 20, SCBD : 18
SCD : 10 ← cheapest!SCDE : 14
SCDE : 14SCDEH : 20
SCDEH : 20SCDEHI : 22, SCDEHB : 26…
SCBF / SCDEHI : 20–22SCDEHIG : 24 ← goal enters
remaining opens ≥ 24terminate

Path S,C,D,E,H,I,G, cost 24 — provably shortest.

1.4 — Who found the shortest? → B

Only Branch-and-Bound (option B) returned the 24-route.

1.5 — What about hh? → B (not admissible)

The one-line proof: if hh were admissible, A* could never lose to BnB — an admissible hh guarantees A* returns the optimal path. A* returned 26 while BnB proved 24 exists, therefore some node's hh exceeds its true remaining cost (the culprit sits on the D–E–H corridor, which hh prices as expensive relative to reality). ⇒ not admissible ⇒ B.

Interactive A* trace

1 / 6
OPEN = { S(g=0, h=26, f=26) }
expandingin OPEN (f=g+h)closedreturned path

Tricks & Tips

Answers: 1.1 S,A,B,F,G · 1.2 S,C,B,F,G · 1.3 S,C,D,E,H,I,G · 1.4 B · 1.5 B